|
 |
|

Anyone who
has had any legal training will be
able to tell you that for a contract
to subsist there must be capacity,
offer, acceptance, consideration and
intention to create legal relations.
One would hope by now
that anyone in the construction
industry would be able to tell you
that you cannot adjudicate unless
that is agreed in writing or all the
terms of the agreement evidenced in
writing. Despite the need for
writing since the Housing Grants
Construction & Regeneration Act 1996
to enable all parties to the
construction process to avail
themselves of the cheaper and
quicker dispute resolution process
of adjudication, many contracts,
some for substantial projects, are
not, or not wholly, in writing. Many
contracts, some for substantial
projects, are not or not wholly in
writing.
The construction process being what
it is, procurement now dragging on
through PQQ, tenders, re-pricing and
re-designing, many contractors and
sub contractors start carrying out
work without terms being agreed
sometimes with draft terms between
the parties still under discussion,
sometimes embodied in drafts,
minutes and exchanges of email. It
is of course perfectly acceptable in
law to have an oral contract. It is
acceptable for the terms of any
agreement to be evidenced in writing
or for there to be a mixture of oral
terms and written terms. However,
beginning work without a formal
written agreement increases the risk
of dispute and contractors and sub
contractors increases the risk of
not getting paid.
In the case of RTS Flexible
Systems v Müller (2010) the
parties commenced the works under a
letter of intent and allowed
themselves 4 weeks to conclude and
sign a contract. The contract was
never executed and terms were
negotiated “subject to contract”.
Usually on the expiry of a letter of
intent term or on the contractor
exceeding the financial limits
imposed in the letter of intent the
Court will not recognise there being
any additional contract or any
additional payment due. Furthermore,
the Court would not usually
recognise a contract on terms that
were agreed “subject to contract”.
In the above case the Court of first
instance found that after the expiry
of the letter of intent a contract
had been concluded. The Judge
considered it was unrealistic to
suppose that the parties had not
intended to create legal relations.
The Court of Appeal, on the same
facts, found that no final agreement
had been reached and no contract
would come into existence unless and
until a written agreement was
executed. The Supreme Court found
that a contract had been concluded
but not that comprised in the draft
exchange between the parties but
some other terms particularly as a
price had been agreed, works had
been undertaken and variations
agreed. This case demonstrates,
given the three different
interpretations by the Court of
first instance, the Court of Appeal
and Supreme Court, that if there are
no clear written terms there will be
considerable uncertainty as to
whether a contract had been
concluded at all, and, if one had
been concluded, then what the terms
of the contract would be. In those
circumstances clearly there is scope
for litigation and a considerable
risk that there will be dispute.
It is therefore imperative that
where possible agreements are
concluded in writing. If no formal
agreement is signed ensure you have
put forward in writing and there is
evidence of agreement about the
scope of works, payment, variations
and time. |
Copyright 2006 - 2011 Taylors Solicitors
»
Print
» |
|
|
|
|
|